Earned Value Management: Are Expectations Too High?

Total Page:16

File Type:pdf, Size:1020Kb

Load more

Earned Value Management: Are Expectations Too High? LTC Nanette Patton Allan Shechet Office of the Surgeon General Savvy Services Inc. Earned Value Management Systems (EVMS) are frequently required on government Automated Information System programs. When implementing EVM, especially for the first time, agencies should train their key managers not only in the EVM process but also in the behaviors and management styles required to avoid major problems that can result from the implementation. While EVM is a useful project management tool, implementing EVM will not solve all the chal- lenges in achieving project goals. Furthermore, given the funding and selection processes for programs, first time EVM implementation can introduce a whole new set of program management challenges. Based on their experience with infor- mation technology (IT) and aerospace projects, the authors identify potential difficulties and risk mitigation strategies to counter those potential difficulties. he President’s Office of Management management control systems, but ject team’s staffing levels and productivity, and Budget (OMB) has asked federal also provides the manager with as well as giving insight into areas of the agenciesT to use a project management dis- timely and consistent cost, sched- work breakdown structure where the cipline known as EVM as a strategy to ule, and progress data. The imple- problems occur. avoid costly IT failures. Other than within mentation of an EVMS ensures EVM compares the following three the Department of Defense (DoD), EVM that cost, schedule, and technical pieces of information: is not well understood by federal agencies aspects of the contract are truly 1. How much work you planned to have [1]. OMB issued its EVM policy guidelines integrated and estimated, and actu- accomplished until now (in dollars or in two memos issued in August 2004 and al progress of the project can be hours) is called the Planned Value (PV). August 2005. In addition to requiring fed- identified. [4] 2. How much you have actually spent eral agencies and their contractors to use until now (in dollars or hours) is called EVM for managing all major IT projects, Actual Cost (AC). the OMB established new reporting “If the budget spend 3. The value, in terms of your baseline requirements. Agencies must include EVM budget, of the work accomplished data when they submit Exhibit 300s, docu- plan shows the project until now (in dollars or hours) is called ments in which they present their business the Earned Value (EV). cases for major IT projects. The OMB over-spending and the The first two pieces of data are compared requires agencies to use EVM to calculate to the EV in terms of differences result- and report each project’s estimated total project schedule ... ing in variances and ratios resulting in per- cost and completion date. slipping, the PM ... formance indexes. While EVM is an effective and useful Basic EVM calculations involve differ- project management tool, there are con- may have no way to ences or ratios with respect to EV: straints within the organizational environ- 1. The difference between EV and your ment of the federal government that make a quantitative plan (PV) is Schedule Variance (SV). impede a smooth implementation of SV = EV - PV. EVM. 2. The difference between EV and your assessment of how bad spending (AC) is Cost Variance (CV). Federal Chief Information the trouble is. CV = EV - AC. Officer (CIO) Council ” 3. The ratio of EV to plan (PV) is your Schedule Performance Index (SPI). Framework SPI = EV/PV. In December 2005, the federal CIO EVM Basics 4. The ratio of EV to cost (AC) is your Council released “A Framework for Program managers (PMs) should manage Cost Performance Index (CPI). CPI Developing EVMS Policy for IT Projects” project cost and schedule performance = EV/AC. [2] to assist agencies in developing their measurements as integrated elements and Positive variance is favorable and negative EVM policies as required by OMB not as separate entities. If the budget is unfavorable. Having an EVM perfor- Memorandum M-05-23 [3] for major IT spend plan shows the project over-spend- mance index that is greater than 1 is favor- projects. The guidance states the following: ing and the project schedule shows mile- able, and less than 1 is unfavorable. stones slipping, the PM may know they CPI is a reading on productivity and EVM is a project management might be in trouble but may have no way SPI is a reading on progress. If there is control tool allowing visibility into to make a quantitative assessment of how good productivity and slow progress, then technical, cost and schedule plan- bad the trouble is. EVMS solves this prob- the project is understaffed. If there is low ning, performance, and progress lem by providing an accurate picture of productivity, then either the project has for major IT projects. EVM not spending and accomplishments related to too much unplanned work or the project only encourages contractors to use a baseline plan. This enables the PM to manager may have estimated poorly and effective internal cost and schedule quickly form conclusions about the pro- the project has more work content than 10 CROSSTALK The Journal of Defense Software Engineering January 2007 Earned Value Management: Are Expectations Too High? Contract Threshold Requirements previously thought. CCoosntrt acor tIncentive >Th$50Mreshold •ReqCuoimrepmliaencnteswith industry EVM standard. That is the essence of EVM; the rest CEqualost ortooIncreAbntivoeve > $50M •• FCorommalpvliaalncidaetiwonithofincdonutsrtarcytoErV’sMEVsMtansdysatredm. are details. EqualThresthoooldr Above •• CFoonrtrmacalt Pvalerifdoarmtioanncoef Rcoenptorrat.ctor’s EVM system. Threshold •• InCteognrtartaecdt MPaesrftoerrmSacncheedulRee.port. DoD EVM Applicability •• InItnetgergartaetdeBdaMsealsinterRSecviheewd.ule. • Ongoing surveillance. The DoD has been using cost and sched- • Integrated Baseline Review. ule controls on aerospace and defense Cost or Incentive < $50M but •• COomngpoliainncgesuwrivtheiillandncusetr.y EVM standard. CLosesst oTr hIncaneUnpptiver >< $$50M20M but •• FCorommalpsliaysncteemwvialthidiantdiounnstryotEreVquMirsetda.ndard. projects since the mid-60s. In the Office Threshold but • Contract Performance Report (tailored). of the Under Secretary of Defense Less Than Upper > $20M • Formal system validationnot required. TEhrqualeshotoold br uAbt ove •• InCteognrtartaecdt MPaesrftoerrmSacncheedulRee(ptaoirlot r(etadi)lo. red). • Integrated Baseline Review (tailored). (Acquisition Technology and Logistics) ELqualowertooThrreAbsholvde • Integrated Master Schedule (tailored). • Ongoing surveillance. policy memorandum dated March 7, Lower Threshold • Integrated Baseline Review (tailored). 2005, the DoD revised its EVM policy to Cost or Incentive < $20M •• EOVMngoopintigonsalur(vriesiklla-bncasee.ddecision). streamline, improve, and increase consistency in CLosesst oTr hIncanentive < $20M •• CEosVtM-beonpetfioitnaalnal(ryisiks-rbeaquseirdded.ecision). EVM implementation and application [5]. LeTsshreTshoalnd • Cost-benefit analysis required. The DoD requirement for EVM applies Threshold to cost or incentive contracts, subcon- Phase Phase Defined tracts, intra-government work agree- TablePh aP1:sheDoDa1:se EVMT hThresholdse DoD ass andess eRequirementss capabilitiPesh,aasenalDyzeefsintehde threat and national ments, and other agreements that meet PPhlaasnnei1:ng TdhefeenDsoeDpoalssiciesssaensddcaepvaebloiplitsierse,soaunralceyzinefsortmheedthprreoagtramndgnuaidtaioncnale. the dollar thresholds prescribed (see proper contractingT vehicle.his guidanc Whene def iappro-nes the requcouldireme setnts theirfor th eownmili tdollarary se rthresholdsvices. under priate,Plann theing businessde fcaseense analysispolicies ashouldnddevelothisps r enewsou rrule,ce inf theyorm ealsod pr ostated,gram gitu isid notanc appro-e. Table 1). This memorandum requires the Phase 2: Thiessgeurviidcaencs teradnesflaintesgtuhidearnceque iinretomaepnlatsnfotor tallheocmatielitarerysosuercrviescetos. Programming accomplish mission requirements. They cost out force objectivessix Table’s application thresholds (total con- beP includedhase 2: in theT hacquisitione services t rapproachanslate guidapriatence i nttoo aexcludeplan to certainalloca tecontractresour ctypeses to from years in the future. tract value including planned options in sectionProgr aofmm theing programaccom acquisitionplish missio nstrat-requiremEVMSents. Trequirementshey cost ou int f otherc eFAR.objec Intiv eaccordancessix then-year dollars [TY$]). egy P(seehase Figure3: 1).yTehaersPrienstihdenftu’stubrued. get is prewithpare dOMB, revie wCirculared, and A-11,sentto PartCon g7,re ssEVMS. is Budgeting This phase concentrateson the funding requirements necessary to Although EVM is not required on PHowever,hase 3: theT hFederale Presid enAcquisitiont’s budget is prrequiredepared , forrevi majorewed ,acquisitionsand sentt oforCo ndevelopmentgress. do the job. contracts, subcontracts, intra-govern- RegulationBudgetin g(FAR) councilThis ph aissuedse conc ae rulentrat einsonregardlessthe fund iofng contractrequire typemen[8].ts n Theecess DoDary t oallows Phase 4: dAosstehsse jmobe.nts are made concerning current and previous resource ment work agreements, and other agree- JulyE 2006xecut iothatn wentall intoocati oeffectns and inw hAugustether the Dexemptions.oD achieved its p Thelanne d pDefenseerformanc e Federal Phase 4: Assessments are made concerning current and previous resource ments valued at less than $20 million
Recommended publications
  • Planning for Organization Development in Operations Control Centers

    Planning for Organization Development in Operations Control Centers

    Federal Aviation Administration DOT/FAA/AM-12/6 Office of Aerospace Medicine Washington, DC 20591 Planning for Organization Development in Operations Control Centers Linda G. Pierce Clara A. Williams Cristina L. Byrne Darendia McCauley Civil Aerospace Medical Institute Federal Aviation Administration Oklahoma City, OK 73125 June 2012 Final Report OK-12-0025-JAH NOTICE This document is disseminated under the sponsorship of the U.S. Department of Transportation in the interest of information exchange. The United States Government assumes no liability for the contents thereof. ___________ This publication and all Office of Aerospace Medicine technical reports are available in full-text from the Civil Aerospace Medical Institute’s publications Web site: www.faa.gov/library/reports/medical/oamtechreports Technical Report Documentation Page 1. Report No. 2. Government Accession No. 3. Recipient's Catalog No. DOT/FAA/AM-12/6 4. Title and Subtitle 5. Report Date Planning for Organization Development in Operations Control Centers June 2012 6. Performing Organization Code 7. Author(s) 8. Performing Organization Report No. Pierce LG, Williams CA, Byrne CL, McCauley D 9. Performing Organization Name and Address 10. Work Unit No. (TRAIS) FAA Civil Aerospace Medical Institute P.O. Box 25082 11. Contract or Grant No. Oklahoma City, OK 73125 12. Sponsoring Agency name and Address 13. Type of Report and Period Covered Office of Aerospace Medicine Federal Aviation Administration 800 Independence Ave., S.W. Washington, DC 20591 14. Sponsoring Agency Code 15. Supplemental Notes Work was accomplished under approved task AM-B-11-HRR-523 16. Abstract The first step in a proposed program of organization development (OD) was to assess organizational processes within the Technical Operations Services (TechOps) Operations Control Centers (OCCs).
  • Performance Management at R&D Organizations

    Performance Management at R&D Organizations

    MTR090189 MITRE TECHNICAL REPORT Performance Management at R&D Organizations Practices and Metrics from Case Examples Carolyn Kahn Sheila McGourty In support of: • FY 2009 Sponsor Performance Management Investigations (POCs: K. Buck and M. Steinbach) • FY 2009 CEM Stakeholder-Driven Performance Management MOIE (POCs: L. Oakley-Bogdewic and K. Buck) April 2009 This page intentionally left blank. MTR090189 MITRE TECHNICAL REPORT Performance Management at R&D Organizations Practices and Metrics from Case Examples Dept. No.: E520 Carolyn Kahn Project No.: 1909M140-AA Sheila McGourty The views, opinions and/or findings contained in this report are those of The In support of: MITRE Corporation and should not be construed as an official government position, • FY 2009 Sponsor Performance Management policy, or decision, unless designated by Investigations (POCs: K. Buck and M. Steinbach) other documentation. • FY 2009 CEM Stakeholder-Driven Performance Approved for public release; Management MOIE (POCs: L. Oakley-Bogdewic and distribution unlimited. K. Buck) Case #09-2188 ©2009 The MITRE Corporation. April 2009 All Rights Reserved. 3 Abstract Performance management supports and enables achievement of an organization and/or program's strategic objectives. It connects activities to stakeholder and mission needs. Effective performance management focuses an organization or program to achieve optimal value from the resources that are allocated to achieving its objectives. It can be used to communicate management efficiencies and to show transparency of goal alignment and resource targeting, output effectiveness, and overall value of agency outcomes or progress toward those outcomes. This paper investigates performance management from the perspective of research and development (R&D) organizations and programs.
  • The Implications of the Organizational Development and Change Supply Chain for ODC As an Academic Discipline

    The Implications of the Organizational Development and Change Supply Chain for ODC As an Academic Discipline

    University of Pennsylvania ScholarlyCommons Building ODC as an Academic Discipline (2006) Organizational Dynamics Conferences May 2006 The Implications of the Organizational Development and Change Supply Chain for ODC as an Academic Discipline Martin F. Stankard University of Pennsylvania, stankard@sas.upenn.edu Follow this and additional works at: https://repository.upenn.edu/od_conf_2006 Stankard, Martin F., "The Implications of the Organizational Development and Change Supply Chain for ODC as an Academic Discipline" (2006). Building ODC as an Academic Discipline (2006). 11. https://repository.upenn.edu/od_conf_2006/11 Academy of Management, Organization Development and Change Division, "Building ODC as an Academic Discipline," 7-8 April 2006. This paper is posted at ScholarlyCommons. https://repository.upenn.edu/od_conf_2006/11 For more information, please contact repository@pobox.upenn.edu. The Implications of the Organizational Development and Change Supply Chain for ODC as an Academic Discipline Comments Academy of Management, Organization Development and Change Division, "Building ODC as an Academic Discipline," 7-8 April 2006. This working paper is available at ScholarlyCommons: https://repository.upenn.edu/od_conf_2006/11 WORKING PAPER MFS-003 DATE: June 23, 2006 PAGE: 1 Implications of a “Supply Chain for ODC as an Academic Discipline The Conference on Organizational Development and Change (ODC) As An Academic Discipline, April 7- 8 2006 International House, University of Pennsylvania Philadelphia, PA By Martin F. Stankard, Affiliated Faculty Center for Organizational Dynamics, School of Arts and Sciences, University of Pennsylvania, Philadelphia, PA Stankard@sas.upenn.edu ABSTRACT This article presents and expands upon the idea of an “ODC Supply Chain” which Dominck Volini of Right Management Consultants and the University of Pennsylvania presented during an Organizational Development and Change Management (ODC) Conference break out session.
  • Organizational Change and Development Chapter 12

    Organizational Change and Development Chapter 12

    Organizational Change and Development Chapter 12 ORGANIZATIONAL CHANGE AND DEVELOPMENT Introduction Change is a constant, a thread woven into the fabric of our personal and professional lives. Change occurs within our world and beyond -- in national and international events, in the physical environment, in the way organizations are structured and conduct their business, in political and socioeconomic problems and solutions, and in societal norms and values. As the world becomes more complex and increasingly interrelated, changes seemingly far away affect us. Thus, change may sometimes appear to occur frequently and randomly. We are slowly becoming aware of how connected we are to one another and to our world. Organizations must also be cognizant of their holistic nature and of the ways their members affect one another. The incredible amount of change has forced individuals and organizations to see “the big picture” and to be aware of how events affect them and vice versa. Organizational development (OD) is a field of study that addresses change and how it affects organizations and the individuals within those organizations. Effective organizational development can assist organizations and individuals to cope with change. Strategies can be developed to introduce planned change, such as team-building efforts, to improve organizational functioning. While change is a “given,” there are a number of ways to deal with change -- some useful, some not. Organizational development assists organizations in coping with the turbulent environment, both internally and externally, frequently doing so by introducing planned change efforts. Organizational development is a relatively new area of interest for business and the professions. While the professional development of individuals has been accepted and fostered by a number of organizations for some time, there is still ambiguity surrounding the term organizational development.
  • The Impact of Organizational Culture on Customer Service Effectiveness

    The Impact of Organizational Culture on Customer Service Effectiveness

    sustainability Article The Impact of Organizational Culture on Customer Service Effectiveness from a Sustainability Perspective 1,2, 1 1 Daniel Metz * , Liviu Ilies, and Răzvan Liviu Nistor 1 Faculty of Economics and Business Administration, Babes-Bolyai University, 400591 Cluj-Napoca, Romania; liviu.ilies@econ.ubbcluj.ro (L.I.); razvan.nistor@econ.ubbcluj.ro (R.L.N.) 2 NTT DATA Romania, 400158 Cluj-Napoca, Romania * Correspondence: daniel.metz@econ.ubbcluj.ro Received: 23 June 2020; Accepted: 28 July 2020; Published: 3 August 2020 Abstract: The conducted study focused on a multinational ITC (Information Technology and Communications) company. Empirical research aimed to evaluate organizational culture based on Denison’s model through four features: capacity development, basic values, customer orientation, and goals and objectives. At the same time, the study analyzed service provided to customers, taking into account its three phases: pre-transaction, transaction, and post-transaction. As research methods, we used a questionnaire-based survey and direct observation. The results of the study demonstrate that the company has a strong culture based on an adequate core value system (shared by company members), innovative and effective human capital management practices, and customer orientation. All characteristics ensure the integration of sustainability principles into strategies, policies, and management practices of the company. At the same time, the authors develop a design and analysis model of the impact of organizational culture features on customer service effectiveness, highlighting that the four organizational culture features are good predictors for improving customer service effectiveness, which promotes an ethical business model and sustainable pursuit of economic, social and environmental performance.
  • Organization Development 101

    Organization Development 101

    Organization Development 101 Two-Hour Presentation From Minnesota Organization Development Network (MNODN) Authenticity Consulting, LLC (763-971-8890); all rights reserved Introduction – Goals of Seminar n Provide brief, basic overview of organization development (“OD”) as profession n Discuss brief, basic overview of general organizational change process n Mention major established models and movements for change n Present numerous additional resources to learn more Authenticity Consulting, LLC (763-971-8890); all rights reserved Introduction – Nature of Session n Challenge to combine info about OD profession and organizational change in 2-hour seminar n Do upfront, 1-hour quick lecture/presentation to breeze through “foundation” info to establish “territory” of OD n Then enhance learning through discussion, questions and answers among attendees n Later enhance learning by reviewing – and applying – additionally suggested resources n Info is in OD Library at www.mnodn.org Authenticity Consulting, LLC (763-971-8890); all rights reserved Defining OD – Ways to Talk About OD n 3 levels can talk about OD n Philosophy/paradigm/values n Theories/models n Tools and techniques n This presentation includes all levels and also OD as a profession Authenticity Consulting, LLC (763-971-8890); all rights reserved Defining OD – Traditional Definition of Process n “Organization Development is an effort planned, organization-wide, and managed from the top, to increase organization effectiveness and health through planned interventions in the organization's 'processes,' using behavioral-science knowledge.” – Beckhard, “Organization development: Strategies and Models”, Reading, MA: Addison-Wesley, 1969, p. 9. n New definitions are evolving Authenticity Consulting, LLC (763-971-8890); all rights reserved Defining OD – A New Definition n “Organization Development ..
  • DOE Project Management News PM EVM Roadside Assists Acquiring Minds Want to Know

    DOE Project Management News PM EVM Roadside Assists Acquiring Minds Want to Know

    Home Director’s Corner EIR/IPR/PPR/ICE/ICR DOE Project Management News PM EVM Roadside Assists Acquiring Minds Want to Know Project Controls Fellowship Program Questions of the Month PMCDP FY 17 Training Strategy Upcoming Training Procedural Change for August 2016 Edition Submitting FPD Packages Recently Certified! Past Newsletter Editions Questions/Comments? DOE Project Management News │ August 2016 Home Director’s Corner Director’s Corner Project Controls Professionals – The Fellowship Has Begun: EIR/IPR/PPR/ICE/ICR To expand our project controls capability and expertise DOE/NNSA- wide, the Certification Review Board (CRB) has established the DOE Project Controls Fellowship Program (PCFP). This Program is intended PM EVM Roadside Assists to identify and further develop a cadre of highly skilled employees (10- 20 designated “Fellows”). Many of these candidates already have a vertical depth of competency in one or more project management Project Controls disciplines (cost, schedule, risk, earned value, etc.) with a horizontal Fellowship Program breadth of understanding in the various disciplines. We want to identify this cadre and make maximum use of their talents, to the benefit of DOE, complex-wide. Questions of the Month Effective management of DOE projects requires a rigorous and disciplined Federal project control’s capability comprised of individuals PMCDP FY 17 Training who have the expertise-- gained first-hand -- to integrate project Strategy controls and project management principles to provide leadership with the requisite accurate project performance information necessary to Upcoming Training Paul Bosco, make informed decisions. We are looking for people who are experts Director of the in Earned Value Management Systems (EVMS) and/or Integrated Office of Project Master Scheduling, and/or other advanced project control methods.
  • 24 Organization Development

    24 Organization Development

    415 24 Organization Development Key concepts and terms • Action research • Integrated strategic change • Group dynamics • Neuro-linguistic programming (NLP) • Intervention • Organizational transformation • Organization development (OD) • Sensitivity training laboratories • Process consulting (T-groups) • Survey feedback • Transactional analysis • Behaviour modifi cation Learning outcomes On completing this chapter you should be able to defi ne these key concepts. You should also know about: • Features of organization • The assumptions and values of development programmes organization development • Organization development activities 416 Organization Design and Development Introduction Organization development (OD) is about taking systematic steps to improve organizational capability. It is concerned with process – how things get done. In this chapter, organization development is defi ned, organization development strategies are examined, consideration is given to the assumptions and values of OD, and OD activities are described. Processes associ- ated with OD for managing change and organizational transformation are dealt with in Chapter 25. Organization development defi ned Organization development is defi ned by Cummins and Worley (2005) as: ‘The system-wide application and transfer of behavioural science knowledge to the planned development, improvement and refi nement of the strategies, structures and processes that lead to organiza- tional effectiveness’. Organization development defi ned, French and Bell (1990) A planned systematic process in which applied behavioural science principles and practices are introduced into an ongoing organization towards the goals of effecting organizational improvement, greater organizational competence, and greater organizational effectiveness. The focus is on organizations and their improvement or, to put it another way, total systems change. The orientation is on action – achieving desired results as a result of planned activities.
  • Supply Chain Involvement in an Engagement: Verification of Marketing and Operational Collaboration

    Supply Chain Involvement in an Engagement: Verification of Marketing and Operational Collaboration

    SUPPLY CHAIN INVOLVEMENT IN AN ENGAGEMENT: VERIFICATION OF MARKETING AND OPERATIONAL COLLABORATION Sumitro Sarkum1, BA. Pramuka2, A.Suroso3, S. Suliyanto4, S. Sutarmin5 1 Doctoral Graduate Programme in Management Science, Economics and Business Faculty, Jenderal Soedirman University and Amik-Labuhan Batu, Rantauprapat-Indonesia 21421. email:sumitro.ulb@gmail.com 2,3,4 Deparment of Economic and Business Faculty, Jenderal Soedirman University, Karangwangkal, Purwokerto-Indonesia 53123. 5 Deparment of Economic and Business Faculty, Peradaban University, Paguyangan, Brebes- Indonesia Abstract The ability of firm's market knowledge in relationships with employee engagement and customer engagement becomes crucial in a marketing strategy. However, the role of marketing function to achieve competitive advantage is still a question of improving business performance. Empirically, there is a need to explore marketing and operational capabilities by involving the supply chain in marketing strategies. Through the views of Dynamic Capability (DC) and service logic, we combine it in a conceptual model that produces several hypotheses. A total of 250 MSME (Micro Small and Medium Enterprises) are involved to answer the questionnaire. Respondents' perceptions reveal that the supply chain has essentially opened itself into an engagement for mutual value creation and sustainability. Our findings also reveal that supply chain engagement can improve business performance and positively mediate employee engagement, but it is unable to mediate customer engagement. In contrast, supply chain engagement is insignificant when market knowledge, customer engagement and employee engagement are directly linked to business performance. In addition, our findings also resulted in an insight for management in optimizing the firm's ability to perform its marketing functions.
  • Farmer Organization Development Strategy (Fods)

    Farmer Organization Development Strategy (Fods)

    GOVERNMENT OF MALAWI MINISTRY OF AGRICULTURE FARMER ORGANIZATION DEVELOPMENT STRATEGY (FODS) 2020 - 2025 2020 - 2025 GOVERNMENT OF MALAWI MINISTRY OF AGRICULTURE FARMER ORGANIZATION DEVELOPMENT STRATEGY (FODS) 2020 - 2025 December, 2020 Department of Agriculture Extension Services Ministry of Agriculture P.O. Box 30145 Lilongwe, MALAWI Ministry of Agriculture | v TABLE OF CONTENTS FOREWORD ........................................................................................................................... vii PREFACE .............................................................................................................................. ix ACKNOWLEDGEMENTS ......................................................................................................... xi LIST OF ACRONYMS/ABBREVIATIONS .................................................................................. xiii GLOSSARY OF TERMS ........................................................................................................... xv 1.0 INTRODUCTION .......................................................................................................... 1 1.1 Background ............................................................................................................... 1 1.2 History of the Farmer Organization Movement in Malawi ............................................ 1 1.3 Rationale for Developing the FODS ............................................................................ 3 1.4 Process of Developing the FODS ...............................................................................
  • ORGANIZATION DEVELOPMENT FUNDAMENTALS Managing Strategic Change

    ORGANIZATION DEVELOPMENT FUNDAMENTALS Managing Strategic Change

    ORGANIZATION DEVELOPMENT FUNDAMENTALS Managing Strategic Change William J. Rothwell, Editor William J. Rothwell, Editor Cavil S. Anderson Cynthia M. Corn Catherine Haynes Cho Hyun Park Aileen G. Zaballero © 2015 ASTD DBA Association for Talent Development (ATD). All rights reserved. Printed in the United States of America. 18 17 16 15 1 2 3 4 5 No part of this publication may be reproduced, distributed, or transmitted in any form or by any means, including photocopying, recording, or other electronic or mechanical methods, without the prior written permission of the publisher, except in the case of brief quotations embodied in critical reviews and certain other noncommercial uses permitted by copyright law. For permission requests, please go to www.copyright.com, or contact Copyright Clearance Center (CCC), 222 Rosewood Drive, Danvers, MA 01923 (telephone: 978.750.8400; fax: 978.646.8600). ATD Press is an internationally renowned source of insightful and practical information on workplace learning, training, and professional development. ATD Press 1640 King Street Alexandria, VA 22314 Ordering information: Books published by ATD Press can be purchased by visiting ATD’s website at td.org/books or by calling 800.628.2783 or 703.683.8100. Library of Congress Control Number: 2014952064 ISBN-10: 1-56286-911-6 ISBN-13: 978-1-56286-911-3 e-ISBN: 978-1-60728-502-1 ATD Press Editorial Staff Director: Kristine Luecker Manager: Christian Green Community of Practice Manager, Human Capital: Ann Parker Associate Editor: Melissa Jones Cover Design: Marisa Kelly Text Design: Kristie Carter-George and Marisa Kelly Printed by Data Reproductions Corporation, Auburn Hills, MI www.datarepro.com Contents Acknowledgments ..............................................................................v Preface ..............................................................................................
  • Project Management Roles & Responsibilities

    Project Management Roles & Responsibilities

    The Center for Business Practices is the research and publishing arm of PM Solutions. For more information, visit www. cbponline.com. the center for business practices ® Project Management Roles & Responsibilities SECOND EDITION J. Kent Crawford Jeannette Cabanis-Brewin Deborah Bigelow Crawford James S. Pennypacker Project Management Roles & Responsibilities Project Management Roles & Responsibilities SECOND EDITION J. Kent Crawford Jeannette Cabanis-Brewin Deborah Bigelow Crawford James S. Pennypacker Center for Business Practices PROJECT MANAGEMENT ROLES & RESPONSIBILITIES ISBN: 978-1-929576-26-5 Headquarters Center for Business Practices 1788 Wilmington Pike Glen Mills, Pennsylvania 19342 USA tel: 484.450.0100 World Wide Web www.cbponline.com The publisher offers discounts on this book when ordered in bulk quantities. For more information, write to Special Sales/Professional Marketing at the headquarters address above. PMBOK® is a trademark and PMP® is a certifi cation mark of the Project Man- agement Institute, Inc. which are registered in the United States of America and other nations. Copyright © 2008 by Center for Business Practices. All Rights Reserved. Neither this book nor any part may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying, microfi lming, and recording, or by any information storage and retrieval system, without permission in writing from the publisher. Current printing (last digit): 10 9 8 7 6 5 4 3 2 1 PRINTED IN THE UNITED STATES OF AMERICA 4 Contents Project